Harrogate and Knaresborough Active Travel schemes progress
Update: March 2026.
|
Project |
Budget Allocation |
Approved funding source |
Updates to date |
Expected delivery date |
|
Oatlands and Wetherby Crossings |
£230,000 |
26/26 Capital Program |
· Wetherby Road crossing construction commenced 6th October 2025, completed 24th October. · Oatlands Drive crossing delivered between 9th & 26th February 2026 |
Complete |
|
ATF 2 Victoria Avenue -pedestrian improvements & resurfacing |
£807,000 & £200,000 |
Active Travel Fund 2 & Capital Programme |
· Complete, minor snagging outstanding to be completed before the end of the financial year. |
Complete |
|
Bilton Crossing
|
110,000 |
S106/ATF5 |
· Funding awarded for delivery of scheme through ATF 5. Consultation on updated designs and TRO’s to commence Q1 26. |
Q3 26 |
|
Killinghall Access Improvements |
TBC |
S106 |
· Surfacing not able to be progressed with current landowner. TRO’s to overcome on street parking issues currently in progress. |
TBC |
|
Otley Road Sustainable Transport Measures |
£710,000 |
NPIF Cold bath road signals upgrade
Otley Road bus stops upgrades
Cold bath Rd 20mph
Access arrangements at Falcon Chiropractic 24
Crossing point western primary school
Improved crossing point from PROW Green lane Ashville college
Review signing for cycle paths
20MPH Arthurs Ave Surrounding streets
Cycle parking/ improved public realm- feasibility stage still Delivery
|
· Tender awarded. Works programmed for May – June 2026
· Likely to be delivered with Otley Road improvements associated with West of Harrogate development
· Additional speed surveys required after roadworks in vicinity of Cold Bath Road are completed.
· Signals team programme has upgrades taking place Q3 2025
· TRO informal re-consultation with CBR 20mph zone
· To be delivered with Green Lane Traffic Calming
· To tie in with cycle priority work, on pause for now
· Crossing assessment currently in progress, traffic calming to be sinusoidal cushions if calming required
· Feasibility stage
|
Q2 26
TBC
Speed surveys to be completed late June 26
Q3 25
Q4 26
TBC
TBC- Not yet programmed.
Q4 26
TBC- Not yet programmed
|
|
20mph’s requiring traffic calming |
130,000/175,000 |
Capital Programme/NPIF |
· Consultation to have commenced by June on all traffic calmed streets. Timeline varies across individual streets, expect to consult with a phased approach. |
Varies |
|
HTIP- Highways Transportation Improvement Package |
|
|
· A report was taken to Environment Executive on 19th December 2025 |
TBC |